- What happened to Lifepointe?
- Why has the rebuild taken so long?
- What is being built?
- Where is construction currently up to?
- What about the Kids and Youth facilities?
- More than a Sunday church
- What happened with the development approval?
- What about parking?
- Christmas at Lifepointe returns during the rebuild
- Lifepointe rebuild timeline
- What happens next?
- Follow the Lifepointe rebuild
- Sources & further reading
More than three years after a devastating fire destroyed much of Lifepointe Baptist Church, the rebuild of the well-known North Buderim community facility is taking shape.
Construction is now well underway at 186 Wises Road, with the project progressing through a staged rebuild that will eventually deliver a new auditorium, foyer, children's and youth facilities and spaces designed for broader community use.
The journey to this point has taken longer than originally hoped, largely due to complications with the church's insurer following the January 2023 fire.
Here's where the Lifepointe rebuild currently stands and what is planned for the site.
What happened to Lifepointe?
On the night of 20 January 2023, a major fire tore through Lifepointe's Wises Road complex.
Around 60 per cent of the structure was involved in the fire, with the church later reporting that approximately 80 per cent of its building had been destroyed.
The main auditorium, offices, foyer, hall and adjoining areas were among the facilities lost.
Fortunately, no one was injured.
Investigations eventually traced the fire to an electrical fault associated with an illuminated exit light.
Read more: Church vows to rebuild after the fire — Sunshine Coast News
Why has the rebuild taken so long?
Soon after the fire, Lifepointe indicated its intention to rebuild, but an unexpected insurance issue significantly complicated the process.
The church's insurer experienced financial difficulties while the claim was being processed and ultimately went into receivership.
Lifepointe did not receive the full insurance payout it had expected, leaving a funding shortfall for the new complex.
The church continued operating throughout this period, establishing temporary facilities and demountable buildings at Wises Road under the name Lifepointe Village, while moving its main Sunday services to nearby Immanuel Lutheran College.
Rather than simply replacing the destroyed building exactly as it was, the church also used the opportunity to redesign the complex around both church and wider community use.
Read more: Church lodges rebuild plans following the fire — Sunshine Coast News
What is being built?
Plans for the rebuilt Lifepointe complex emerged publicly in 2024.
The new facility has been designed to provide considerably more flexibility than the former building, allowing different areas to be used by community groups and activities throughout the week.
Plans include:
- a new main auditorium
- a village-green-style foyer and gathering area
- children's facilities
- youth facilities
- community-use spaces
- upgraded technology and audio-visual facilities
- covered connections between buildings
- landscaping
- parking and supporting infrastructure
One of the major design changes is the auditorium itself.
Rather than operating only as one large space, the new auditorium is designed so it can be divided into three separate rooms, allowing smaller groups to use parts of the building independently.
The complex has also been designed around a central courtyard-style area, with the new buildings oriented more towards bushland on the eastern side of the property rather than neighbouring homes.
Read more: Church lodges rebuild plans following the fire — Sunshine Coast News
Where is construction currently up to?
Physical rebuilding began in late 2025.
At the time, Lifepointe said the main rebuild was targeting completion by the end of September 2026, although parts of the project would need to be delivered later because of the funding shortfall.
The church's current information indicates the project is now progressing through its staged rebuild.
Lifepointe says more than $500,000 has been raised towards the project, with the next stage focused on completing the Kids Wing and foyer.
A further $300,000 is being sought to help complete the church's current vision for these areas.
Importantly, while September 2026 was previously identified as the target for completion of the main rebuild, Lifepointe's current information still describes the project as progressing through its stages.
Sunday services also continue to be advertised at Immanuel Lutheran College rather than the Wises Road complex.
For that reason, the full Wises Road facility should not yet be considered back to normal operation.
Current information: Lifepointe's Rebuild Together page
What about the Kids and Youth facilities?
The children's and youth facilities are one of the major components of the overall vision.
When construction began in 2025, plans included a two-storey youth and children's building, although Lifepointe indicated this component would be delayed until sufficient additional funding was available.
Fundraising has since allowed the project to move forward.
The church's current rebuild information identifies completion of the Kids Wing and foyer as part of its next stage.
Exactly when all components of the children's and youth facilities will be completed has not yet been confirmed.
More than a Sunday church
One of the notable aspects of the rebuild is the emphasis on creating a facility that can be used throughout the week.
Before the fire, Lifepointe hosted a range of community activities alongside its church services, and those activities have continued in reduced facilities during the rebuild.
Programs have included playgroups, children's and youth activities, craft groups and other community programs.
The church has described its intention for the new complex to operate more like a community hub, with spaces capable of accommodating different groups and activities rather than sitting unused outside Sunday services.
That approach is reflected in features such as the divisible auditorium, central gathering areas and dedicated youth and children's spaces.
For North Buderim, it means the project is more than simply replacing the building that was lost in 2023.
What happened with the development approval?
Lifepointe was already an established and approved use at the Wises Road site.
Because the proposed replacement complex differs from the previous buildings, however, the church lodged an application seeking changes to its existing development approval.
Planning documents reported in 2024 showed proposed site coverage increasing to approximately 25.5 per cent, compared with 17.2 per cent under the site's original approval.
The application also continued to recognise the property's community-centre function alongside its church use.
Development applications and associated planning documents can be searched through Sunshine Coast Council's official Development.i system.
Sunshine Coast Council — Development.i
What about parking?
Parking was also considered as part of the new design.
The rebuild plans reported in 2024 provided for:
- 180 sealed car spaces
- four accessible spaces
- three bus spaces
- eight motorcycle spaces
- 20 bicycle spaces
The church indicated this was expected to cater for its normal activities.
For unusually large events, Lifepointe has historically relied on additional off-site parking arrangements and shuttle services.
This is particularly relevant for Christmas at Lifepointe, which has previously attracted tens of thousands of visitors.
Read more: Church lodges rebuild plans following the fire — Sunshine Coast News
Christmas at Lifepointe returns during the rebuild
The annual Christmas at Lifepointe event has become one of the church's most recognisable connections with the wider Sunshine Coast community.
The event continued in a modified format following the 2023 fire, with the former auditorium slab used for an outdoor event that year.
It was cancelled in 2024 while preparations for the rebuild progressed.
With construction underway, Christmas at Lifepointe returned in 2025, using available areas of the property while construction zones remained fenced off.
The event included many of its familiar attractions, including the Tunnel of Lights, musical production, animal farm and family activities.
Its return was an important milestone for the Wises Road site even while the new church remained under construction.
Read more: Beloved event returns as the church rebuild begins — Sunshine Coast News
Lifepointe rebuild timeline
20 January 2023 — Fire destroys the complex
A major fire destroys much of Lifepointe Baptist Church's Wises Road complex.
2023 — Temporary facilities and relocated services
The church establishes temporary facilities at the property and relocates its main Sunday services to Immanuel Lutheran College.
2023–2024 — Insurance complications delay the rebuild
The rebuild is delayed as Lifepointe deals with significant complications involving its insurer and eventual funding shortfall.
2024 — Redesigned plans lodged
Plans for a redesigned church and community facility are lodged as part of changes to the existing development approval.
December 2024 — Christmas at Lifepointe cancelled
Christmas at Lifepointe is cancelled as preparations for the rebuild progress.
Late 2025 — Construction begins
Physical construction of the new Lifepointe complex begins.
December 2025 — Christmas at Lifepointe returns
Christmas at Lifepointe returns while construction continues around the event.
2026 — Staged construction continues
Construction continues, with the project being delivered in stages.
September 2026 — Current position
Lifepointe reports more than $500,000 has been raised towards additional works, with the Kids Wing and foyer forming the next focus of the rebuild.
What happens next?
The main thing to watch now is the transition from an active construction site back into a fully operational community facility.
Lifepointe's current plans are focused on continuing the staged rebuild, including the Kids Wing and foyer, while additional fundraising continues.
A confirmed date for the return of Sunday services to the new Wises Road auditorium has not been identified in the current information reviewed for this article.
Until then, Lifepointe Village continues operating at 186 Wises Road, while Sunday services are being held nearby at Immanuel Lutheran College.
After more than three years of temporary facilities, insurance complications, planning and construction, the new buildings now taking shape represent the final chapters of a lengthy rebuilding process for one of North Buderim's longstanding community facilities.
Follow the Lifepointe rebuild
We'll continue updating this article as further milestones are reached, including completion of the new auditorium, Kids Wing and foyer and the eventual return to full operation at Wises Road.
NorthBuderim.com.au covers local development, community news, businesses, events and property updates from across North Buderim.
Sources & further reading
For residents who would like to look further into the project, these are some of the principal sources used to prepare this guide:
- Lifepointe Baptist Church — Rebuild Together — Current information directly from Lifepointe about the rebuild, fundraising and next stages. View Lifepointe's Rebuild Together updates
- Sunshine Coast News — August 2024 — Detailed coverage of the proposed replacement complex, planning application, parking and community-use design. Read: Church lodges rebuild plans following the fire
- Sunshine Coast News — November 2025 — Construction progress, funding situation, proposed facilities and the original September 2026 completion target. Read: Beloved event returns as the church rebuild begins
- Sunshine Coast News — January 2023 — Coverage of the original fire and immediate response. Read: Church vows to rebuild after the fire
- Sunshine Coast Council — Development.i — Council's official system for viewing development applications and associated documents. Search Development.i